New interchange at I-77 and County Road 80. The diamond shaped interchange included construction of a five-lane bridge overpass over I-77 to replace a two-lane bridge, replacement of a bridge over Sugar Creek, new entrance and exit ramps to the interstate, and the relocation of a portion of Progress Street.
ODOT I-77/County Road 80 Interchange
Dover, Ohio
Project Description
Project Highlights
- Steel girder structure over I-77
- Pre-cast beam structure over Sugar Creek
- Over 7,500 lf of driven pipe pile
- 5,638 sf of MSE walls
- 4,855 lf of storm drainage
- 180,000 cy of roadway embankment
- Demolition of North and South bound rest areas
- Demolition of structures over I-77 & Sugar Creek
- Wetlands construction